Lap timer for observed cycle times.
Use it on the shop floor to time real cycles. Tap a lap for each cycle, add comments for interruptions, and it gives the average, spread and standard deviation, ready to paste into Excel.
Keyboard: S starts and stops, L records a lap, R resets, C jumps to the comment box. Up to 100 laps.
Fluctuation = longest lap minus shortest lap. Standard deviation uses the sample formula. Lap times are in seconds.
A time study captures how long each work element really takes on the floor, which is the starting point for takt, balancing and standard work.
Ten cycles of a packing job give times between 52 and 81 seconds. Nine cycles are under 58 seconds. The 81-second cycle came from a missing carton, which is a material supply problem rather than an operator problem, so it is fixed separately and the standard is set at about 55 seconds.
Usually at least 10. More cycles are needed when the process varies a lot.
Use the lowest repeatable time for standard work and the average for capacity planning. Investigate any large gaps between the two.
Yes. Signed-in users can download the tool and use it offline on a tablet or laptop.